Return on invested capital is achieved only after projects close and assets go to work. Stratex Online brings completed projects, the assets they became, ongoing leases and subscriptions, and the actual return on each investment into one data source, so executives can see where capital is performing and steer the next round on evidence.

Clients of IQX Business Solutions, the team behind Stratex Online
Rated 5.0 on Gartner Peer Insights for capital investment management (5 reviews) | SOC 2 Type 2 compliant | ISO 27001 certified
How do you capture the value of a completed capital project?
Once delivery ends, four pieces of work decide what a capital project is worth: closing it out, capitalizing its cost, reviewing its return and managing the commitments it leaves behind. Stratex Online brings the information behind all four into one data source, connected in a seamless process, so decision makers can see each investment through to its actual return.
When can you call a capital project complete?
A capital project is complete only once it has crossed three finish lines, which can fall months apart: the asset is in service, its cost is capitalized, the project is closed to new spend with open purchase orders closed out, and unused budget is returned to the investment program.
- 1
Operational completion
The asset is accepted and running. Operational readiness confirms the people, procedures and spares are in place before handover.
- 2
Financial completion
Commitments are cleared, final costs are capitalized to the right assets, and the project is closed to new spend.
- 3
Investment completion
Any unused budget allocation is returned to the investment program for redeployment.
How should leases and subscriptions be governed through closeout?
When a capital project is approved, the preferred funding is sometimes a lease or subscription rather than an outright purchase. While a purchased asset is capitalized onto the fixed asset register and stays visible there, lease payments and subscription fees join business-as-usual costs and lose their link to the investment that created them. The investment’s lifetime cost is then understated, and its return looks better than it is.
Keep every lease and subscription on the investment’s record at closeout, with its term, owner and renewal date, so its full cost counts toward the investment’s return. Each renewal then becomes a chance to check the commitment against the original business case and assess how the investment has actually performed, before it rolls on.
| Question | Buy | Lease | Subscribe |
|---|---|---|---|
| At closeout | Capitalized to the fixed asset register at final cost | Payments are often budgeted as operating spend, though under IFRS 16 and ASC 842 most leases longer than 12 months also bring a right-of-use asset and a lease liability onto the balance sheet | Fees start in the operating budget |
| Where the cost sits after closeout | On the register, depreciated over its useful life | In operating spend, often coded as business-as-usual | In operating spend, often coded as business-as-usual and renewing automatically |
| What it commits | Capital up front, then maintenance and eventual replacement | Fixed payments for the term | Recurring fees that renew each term |
| The next decision | Replace, refurbish or dispose at the end of useful life | Renew, return or buy out at the end of the term | Renew, resize or replace at each renewal |
Leases and subscriptions that never reached a business case are a separate risk, governed as strategic operational expenditure; see 5 signals a capitalization threshold will never catch. For software, see is SaaS capex or opex?
Did your capital investments deliver the return their business cases predicted?
A capital investment can only be shown to have delivered its business case if it is tracked from approval to result. The business case predicts a return. A post-implementation review compares that prediction with the actual cost, benefits, NPV and payback once the asset is running, and explains any gap. Post-implementation reviews show where forecasts tend to run high or low, and that evidence sharpens how the next round of investments can be assessed, improving return on invested capital over time.
In Stratex Online, each post-implementation review sets the original scores and financial projections of the business case alongside its reassessed scores and actual results, and the insights it records are published to the people who prepare, score and approve the next business cases. Corrective actions are assigned so erroneous assumptions or processes are rectified before the next round of approvals.
Return delivered against the business case, completed investments by reason
-
Replacement94%
-
Sustainability88%
-
Growth and saving72%
-
Information technology61%
AI insight
Growth and technology cases are delivering under three quarters of their predicted return. Ask for stronger benefit evidence in the next round.
How can AI use completed capital projects to improve future investment decisions?
AI uses the actual experience of completed capital projects to improve future investment decisions. By comparing each investment’s actual results with its business case, AI can help explain where and why outcomes differ, and learn from those outcomes which features of a proposal predict success. That gives executives evidence to take to the board on which business case assumptions held and which need stronger support, so the next round can be assessed on firmer ground.
For the board to trust those recommendations, the outcomes behind them need to be governed and held on one record, and the people accountable for each investment need to stay the final decision makers. See how AI can improve every pillar of your CapEx process
How did last year’s completed investments perform against their business cases, and what drove the variances?
14 of 18 completed investments met or beat their predicted return. The 4 that missed were all growth and saving cases.1
| Investment reason | Met case | Return vs prediction |
|---|---|---|
| Replacement | 6 of 6 | 94% |
| Sustainability | 4 of 4 | 88% |
| Growth and saving | 4 of 8 | 72% |
The main driver was vendor performance. 3 of the 4 business cases used efficiency figures quoted above the plant’s normal operating point.2
For the current round, consider requiring vendor claims at your own operating point. 2 growth proposals don’t meet that yet.3
Why do finance teams choose Stratex Online for asset capitalization and asset lifecycle management?
At closeout, finance needs to know that cost reached the right assets, that the register is accurate and that each investment delivered its business case. Stratex Online governs capitalization, register changes, ongoing commitments and the review of each return against the approved investment, in one place.

Decades of closeout and capitalization experience
The consultants who configure and support Stratex Online bring decades of experience in capitalization, asset registers and post-implementation review.
Capitalize asset costs accurately and on time
Allocation rules on each work breakdown structure (WBS) element determine which assets related project costs are capitalized to when the asset goes into service.
Every register change approved
Asset creation, changes, transfers, disposals and capitalizations are all approved before they reach the fixed asset register, to ensure accounting completeness, accuracy and validity.
A register that matches the site
Asset inspection and condition assessment record each asset’s existence, condition and location, and a discrepancy becomes a pre-filled transfer, revaluation or disposal for approval.
Reviews routed to the right sign-off
Selection rules decide which completed investments are reviewed, and each review moves through every role that must sign off, from project manager to review board.
Works with what you run
Connects to SAP, Oracle, Microsoft Dynamics 365, NetSuite and other ERPs, and to your FP&A and PPM tools, so existing systems stay in place.
Where does closeout and capitalization fit in CapEx management?
Closeout and capitalization is the fourth of four pillars in CapEx management software from Stratex Online, which keeps one record for each investment from first idea to realized benefit. It closes the loop: what each review learns goes back to the people setting long-range plans and approving the next round of capital.
Frequently asked questions
When should construction in progress be capitalized?
Construction in progress should be capitalized when the asset is ready for its intended use. Under IFRS, US GAAP and the local standards based on them, that is when depreciation starts, and it can be months before the last invoice arrives or the project is financially closed. Capitalize cost against the assets it belongs to as it arrives, and settle any late costs to those same assets, so depreciation and asset values stay accurate.
Should a capital project be closed before every invoice has arrived?
Yes, a capital project can be closed before every invoice arrives, once the work is accepted and the remaining costs are known. Project accounting is based on the goods and services received, not the timing of invoices or payments. Close the project to new spend so unrelated charges can’t land on it, accrue the known late costs such as retentions and final invoices, and settle them to the same assets when they arrive. Waiting for the last invoice keeps the project open for months and blurs its final cost.
What should happen to unspent budget when a capital project closes?
Unspent budget should be released once final costs are known. Budget left on a closed project ties up capital the business could invest elsewhere. Return it to a budget pool for reallocation to other approved projects, or back to the capital plan, and record the decision against the investment so its final cost and underspend stay visible. See capital planning and budgeting.
Who owns a capital investment after the project team hands over?
Ownership of a capital investment should be named before approval, because the project team’s role ends at handover. Someone runs the asset and owns its benefits, someone owns its value on the register, and the sponsor stays accountable for the return. Record each owner on the investment, so every question after closeout has someone to answer it.
Which module should we start with?
Start with the module that covers your greatest exposure. If completed projects wait to be capitalized or the register is hard to trust, start with asset control. If the board asks whether investments delivered, start with post-implementation review. If projects stay open after handover, start with project closeout, and if renewals pass undecided, start with leases and subscriptions. Each module joins the same record.
How long does it take to get closeout and capitalization running in Stratex Online?
Stratex Online is a ready-to-run SaaS solution. A typical implementation, covering configuration to your approval rules, the ERP connection and training, takes two to four months. An opening asset register can be loaded from a spreadsheet before the ERP connection is set up, so work can start early.
Can we try Stratex Online before we buy?
Yes. You can start a 30-day trial of the Stratex Online core platform, or request a demo to see how closeout and capitalization fit the way you close and capitalize projects.